Here's the process/timeline
- Meet with loan officer
- Meet with electrical
- Meet with flooring
- Mortgage loan approval (required within 45 days of signed agreement)
- Pre-construction meeting
- Customer Involvement Meeting
- Pre-Drywall Meeting
- Personal Home Inspection (I'm having this done - it's not required)
- Pre-Settlement Orientation
- Closing
Construction will probably begin in September and be done by early December. So we are doing a "hurry up and wait". I'm hurrying up on the first 4 items above in yellow and waiting for a few months.